Phase 4 construction overview

The following is an overview of Incheon International Airport's phase 4 construction project.

Phase 4 construction overview

Phase 4 construction will open the era of over 100 mil. passengers for Incheon International Airport.

Incheon International Airport plans to complete phase 4 construction by 2024, which will bring it to the center stage of the world beyond the hub airport status in Northeast Asia.

Construction Period 2017 - 2024
Construction Items

Expansion of Terminal 2 (+29 mil. PAX/year)

One runway (Runway 4: 3,750m) (2.3 miles)

Aprons, parking lots, roads, etc.

Project Cost About 4.8 tril won (412 mil. USD)
  • Flights
    600,000
  • Passengers
    106mil. PAX
  • Cargo
    6.3 mil. tons

Phase 4 construction status

1Expansion of Terminal 2 (347,000㎡) (34.7 ha) 10T2 long-term parking building, road parking lots
2Expansion of Traffic Center 2 (86,000㎡) (8.6 ha) 11T2 long-term parking lot
3Construction of Runway 4 (3,750 x 60m) (2.3 miles x 0.03 miles) 12Expansion of T2 access road (3.52㎞) (2.1 miles)
4Rapid Exit Taxiway & Vertical Taxiway 13T1 southern connecting road (0.97㎞) (0.6 miles)
5Attached aprons (34) 14T1-T2 connecting road (3.87㎞) (2.4 miles)
6Remote aprons (28) & Deicing aprons (11) 15Catering facilities
7Cargo aprons (13) 16Ground handling repair facilities
8MRO 17Airport logistics complex (Phase 3)
9FBO 18Fueling facilities

Economic effects

  • Production 9.3 tril won
    (797 mil. USD)
  • Added value 3.3 tril won
    (283 mil. USD)
  • Job creation 60,000 hired

Aims of phase 4 construction

We Connect Lives, Cultures and the Future

Incheon International Airport will never cease to face challenges.
The phase 4 construction will provide a better, even more convenient airport to passengers.
With the goal of becoming a leading value creator in the aviation industry, Incheon Airport is moving forward at this very moment with views to strengthen the aviation network and establish the airport economic zone.
The phase 4 construction will bring production outcomes and added values worth about 13 trillion won and create about 60,000 high-quality jobs, making Incheon Airport a superb model for realizing social values such as human-centered approach and win-win development among local societies.

  • Better airport

    Smart airport used by 106 mil. people
    Environmentally-friendly airport, art airport

  • Value creation

    Connecting the world
    Establishing the aviation network and the airport economic zone

  • Human-centered

    Connecting the airport and humans
    Good jobs, safe workplace

  • Win-win development

    Connecting the airport and regions
    Development with the local societies

Phase 4 Construction Scale

Up to phase 3 phase 4
  • Passenger capacity
    77 mil. PAX
    29 mil. PAX
    (106 mil. PAX)
  • Runway
    3 Runways
    1 runways
    (4 runways)
  • Terminal 1
    507,000㎡ (50.7ha)
    507,000㎡ (50.7ha)
  • Terminal 2
    388,000㎡ (33.8 ha)
    347,000㎡ (34.7 ha)
    735,000㎡ (73.5 ha)
  • Concourses
    167,000㎡ (16.7ha)
    167,000㎡ (16.7ha)
  • Flights capacity
    500,000
    100,000
    600,000
  • Cargo capacity
    5 mil. tons
    1.3 mil. tons
    6.3 mil. tons
  • Project cost
    13.2 tril. won (11 bil. USD)
    4.8 tril. won (4 bil. USD)
    18.0 tril. won
    (15 bil. USD)