Phase 4 construction overview
The following is an overview of Incheon International Airport's phase 4 construction project.Phase 4 construction overview
Phase 4 construction will open the era of over 100 mil. passengers for Incheon International Airport.
Incheon International Airport plans to complete phase 4 construction by 2024, which will bring it to the center stage of the world beyond the hub airport status in Northeast Asia.
Construction Period | 2017 - 2024 |
---|---|
Construction Items |
Expansion of Terminal 2 (+29 mil. PAX/year) One runway (Runway 4: 3,750m) (2.3 miles) Aprons, parking lots, roads, etc. |
Project Cost | About 4.8 tril won (412 mil. USD) |
- Flights 600,000
- Passengers 106mil. PAX
- Cargo 6.3 mil. tons
Phase 4 construction status
1Expansion of Terminal 2 (347,000㎡) (34.7 ha) | 10T2 long-term parking building, road parking lots |
2Expansion of Traffic Center 2 (86,000㎡) (8.6 ha) | 11T2 long-term parking lot |
3Construction of Runway 4 (3,750 x 60m) (2.3 miles x 0.03 miles) | 12Expansion of T2 access road (3.52㎞) (2.1 miles) |
4Rapid Exit Taxiway & Vertical Taxiway | 13T1 southern connecting road (0.97㎞) (0.6 miles) |
5Attached aprons (34) | 14T1-T2 connecting road (3.87㎞) (2.4 miles) |
6Remote aprons (28) & Deicing aprons (11) | 15Catering facilities |
7Cargo aprons (13) | 16Ground handling repair facilities |
8MRO | 17Airport logistics complex (Phase 3) |
9FBO | 18Fueling facilities |
Economic effects
-
Production 9.3 tril won
(797 mil. USD) -
Added value 3.3 tril won
(283 mil. USD) -
Job creation 60,000 hired
Aims of phase 4 construction
Incheon International Airport will never cease to face challenges.
The phase 4 construction will provide a better, even more convenient airport to passengers.
With the goal of becoming a leading value creator in the aviation industry, Incheon Airport is moving forward at this very moment with views to strengthen the aviation network and establish the airport economic zone.
The phase 4 construction will bring production outcomes and added values worth about 13 trillion won and create about 60,000 high-quality jobs, making Incheon Airport a superb model for realizing social values such as human-centered approach and win-win development among local societies.
-
Better airport
Smart airport used by 106 mil. people
Environmentally-friendly airport, art airport -
Value creation
Connecting the world
Establishing the aviation network and the airport economic zone -
Human-centered
Connecting the airport and humans
Good jobs, safe workplace -
Win-win development
Connecting the airport and regions
Development with the local societies
- Phase 4 Construction Scale
- Process Rate
- Milestones
- Project Management Plan
Phase 4 Construction Scale
-
Passenger capacity
77 mil. PAX(106 mil. PAX)29 mil. PAX
-
Runway
3 Runways(4 runways)1 runways
-
Terminal 1
507,000㎡ (50.7ha)507,000㎡ (50.7ha)
-
Terminal 2
388,000㎡ (33.8 ha)735,000㎡ (73.5 ha)347,000㎡ (34.7 ha)
-
Concourses
167,000㎡ (16.7ha)167,000㎡ (16.7ha)
-
Flights capacity
500,000600,000100,000
-
Cargo capacity
5 mil. tons6.3 mil. tons1.3 mil. tons
-
Project cost
13.2 tril. won (11 bil. USD)18.0 tril. won4.8 tril. won (4 bil. USD)
(15 bil. USD)