Overview of Incheon Airport Construction Phases 1-3
Construction Phases 1-3 of Incheon International AirportOverview
- Phase 1
- Phase 2
- Phase 3
-
Phase 1(1992~2001)
1992. 11 101 months 2001. 03
- Terminal 1 507,000m² (50.7 ha)
- Runway 1&2 2 Runway
- Aprons Passengers 60 / Cargo 24
- 1992. 06. 16Announcement of the new metropolitan airport construction project
- 1996. 05. 23Commencement of Terminal 1 construction
- 2001. 03. 29Opening of Incheon International Airport
-
Phase 2(2002~2008)
2002. 01 77 months 2008. 06
- Concourse 167,000m² (16.7 ha)
- Runway 3 1 Runway
- Aprons Passengers 49 / Cargo 12
- 2004. 06. 28Commencement of earthwork and piling
- 2007. 07. 30Completion of Runway 3 paving
- 2008. 06. 20Completion and opening of Phase 2 construction
-
Phase 3(2009~2017)
2009. 06 103 months 2017. 12
- Terminal 2 388,000m² (38.8 ha)
- Aprons Passengers 54 / Cargo 11
- 2009. 06. 30Announcement of change in the initial plan (phase 3)
- 2013. 06. 14Commencement of earthwork and piling for Terminal 2
- 2018. 01. 18Opening of Incheon International Airport Terminal 2
Aerial view of Incheon International Airport
Incheon Airport at Present
Item | At Present | |
---|---|---|
Terminal Area | Terminal 1 | 507,000㎡ (50.7 ha) |
Terminal 2 | 388,000㎡ (38.8 ha) | |
Concourse | 167,000㎡ (16.7 ha) | |
Capacity | Passengers | 77 mil. PAX |
Cargo | 5 mil. tons | |
Flights | 0.5 mil. times | |
Runway | Runway 1, 2 (phase 1) | 2 Runway (3,750 × 60m / 2.3 × 0.03 miles) |
Runway 3 (phase 2) | 1 Runway (4,000 × 60m / 2.5 × 0.03 miles) | |
Apron | Passengers | 163 |
Cargo | 47 | |
Baggage Handling System (BHS) | - | 141km(88 miles) |